menu

Martin GmbH

08.02.2018

Foshan Nanhai III, People’s Republic of China
Construction of two additional combustion lines.

On 15 November 2017, Mitsubishi Heavy Industries Environmental [&] Chemical Engineering (MHIEC) was awarded the contract to supply 2 waste-fired steam generators for the extension (phase III) of the Nanhai Garbage Incinerating Power Plant in Foshan, Guangdong province.[nbsp]The combustion lines will be equipped with MARTIN reverse-acting grates, each with a throughput of 750 Mg/day. The heat released will be used to generate electricity. The generator has a capacity of approx. 40 MW.[nbsp]Start-up is planned for the year 2019.