Scheuch cooperates in successful retrofit project

21.05.2024

As part of modernisation measures at the Pirmasens waste incineration plant, the first of a total of two electrostatic precipitator lines was recently replaced.

As a reliable partner, ESWET member Scheuch created a customised concept that enabled the inspection time to be reduced to a minimum.

Thanks to a high degree of pre-assembly, a tightly synchronised project schedule for the disassembly and installation work as well as day and night shifts, Scheuch service technicians were able to complete the conversion of the electrostatic precipitator line in a record time of just 19 days.