Scheuch cooperates in successful retrofit project
As part of modernisation measures at the Pirmasens waste incineration plant, the first of a total of two electrostatic precipitator lines was recently replaced.
As a reliable partner, ESWET member Scheuch created a customised concept that enabled the inspection time to be reduced to a minimum.
Thanks to a high degree of pre-assembly, a tightly synchronised project schedule for the disassembly and installation work as well as day and night shifts, Scheuch service technicians were able to complete the conversion of the electrostatic precipitator line in a record time of just 19 days.
Top photo: The Pirmasens project. Credit: Scheuch GmbH
Other members news
Doosan Lentjes signs contract for new sewage sludge treatment plant in Germany
15.05.2026ESWET member Doosan Lentjes has been awarded two lots for the new sewage sludge treatment plant in Cologne. The company…
Ramboll, welcome to ESWET
30.04.2026ESWET continues to grow with the addition of a new member, Ramboll. The company brings decades of engineering know‑how and…
Celebrating a new ESWET member
28.04.2026ATS Walter Materials Handling has joined ESWET as the association’s new member. ATS Walter Materials Handling is a French company…